PROJECT FILE № PST-P04 63/6.9 kV · MIDDLE EAST

Ardakan Steel Substation

Construction of Ardakan Steel 63/6.9 kV substation with extension of two 63 kV line feeders, a 230 kV transformer feeder, and a connected 63 kV transmission line.

Ardakan Steel Substation — Powerst project FIELD RECORD · PST-P04
Specification
CategoryHV Substation
RegionMiddle East
Voltage Class63/6.9 kV
Contract ModelPC / EPC
StatusCompleted · In Service
Delivery

Delivered within Powerst’s substation delivery scope in the Middle East, the work covers the complete chain — from engineering coordination and equipment sourcing through civil works, electromechanical erection and protection integration — to testing and energization at the 63/6.9 kV level.

Scope Of Work
  • Detailed electrical & civil design — single-line diagrams, protection coordination, layout
  • Supply & factory inspection of primary equipment — transformers, switchgear, CT/VT
  • Civil works — foundations, control building, cable trenches and yard grading
  • Electromechanical erection, busbar and gantry installation
  • Protection, SCADA and telecom system integration
  • Testing, commissioning and staged energization